On 8th December 2025, the Standing Committee on Energy presented its report on ‘Performance Evaluation of Solar Power Projects in the Country’ in the Lok Sabha.
Major Issues Highlighted and Recommendations
Inadequate Storage Capacity
- Variability in generation is one of the biggest issues with renewable energy such as solar.
- Against 243 GW of installed renewable capacity, current storage capacity is around 5.5 GW.
- The main reason for slow development of storage capacity is high costs.
- Recommendation: Provide grants to research institutions to conduct storage-related R&D for indigenisation which could bring down prices.
Domestic Manufacturing of Solar Panels
- India remains dependent on import ....
Do You Want to Read More?
Subscribe Now
To get access to detailed content
Already a Member? Login here
Take Annual Subscription and get the following Advantage
The annual members of the Civil Services Chronicle can read the monthly content of the magazine as well as the Chronicle magazine archives.
Readers can study all the material since 2018 of the Civil Services Chronicle monthly issue in the form of Chronicle magazine archives.
Economy Watch
- 1 PFRDA Sets Up Panel for NPS Assured Payouts Framework
- 2 Government Notifies Coking Coal as Critical & Strategic Mineral
- 3 Steel Slag: Transforming Industrial Waste into a Strategic Resource
- 4 India Energy Week 2026
- 5 Strategic Roadmap for a Globally Integrated Food Processing Sector
- 6 RBI’s Revised Guidelines on Priority Sector Lending
- 7 Reserve Bank - Integrated Ombudsman Scheme, 2026
- 8 Tax Residency Certificate (TRC)
- 9 'Tex-RAMPS' Scheme
- 10 A Decade of Startup India: Scaling Innovation; Shaping India’s Growth Story